> Abstract: Must consider very many factors
for a correspondence electrical power system choice rectification
module. Now, day by day is fierce along with the correspondence
market competition, it is necessary to choose the most superior power
source plan to satisfy the market requirement. The careful
appraisal all movements request could to choose the module to have the
significant influence, this article studies the module coolant
conditions, the input voltage scope, the output has limited flows the
characteristic and the operating temperature scope and so on the many
kinds of factors to chooses the electrical power system plan the
important influence. Key word: Correspondence power source rectification
module choice 1 introduction Must consider very many factors for a
correspondence electrical power system choice rectification module.
In the past, the big monopoly telecommunication company
frequently chose ?the remainder very big system plan. But, is
day by day intense along with the global market competition, this
choice way will be cannot be taken. In order to optimize a power
source power supply plan, it is necessary carefully to inspect many
correlation factors, including the product performance and the price
question, can satisfy the end-user like this by the most economical
way the request. The various countries in the law unceasingly to the
product security and EMC proposed the new request, causes the choice
power source plan the condition to be harsher. Provides the
most superior plan for each application situation is necessary, but
starts for this to design each system actually is not feasible from
the beginning. Feasible is the use standard module disposes the
system. The rectification module is the electrical power system
heart, elects the module is not correct, is very difficult to provide
the most superior electrical power system disposition. This
article has studied with the module related many factors as well as
the module movement environment, and provides the choice
correspondence electrical power system rectification module from the
logic the method. This article involves the scope only to be restricted in
single-phase 200W ~ 6kW the rectification module. But many
mentalities may apply on other power sources. 2 coolant conditionses - forced-air cooling and
self-cooling choice A system coolant conditions has the extremely
tremendous influence to the rectification module choice. Some
systems request natural cooling (abbreviation self-cooling), some may
accept the ventilator to cool (abbreviation forced-air cooling).
Under the similar power, the same level condition, the
forced-air cooling and the self-cooling module biggest difference lies
in the contour size and cost how many. In the western big
telecommunication company tradition chooses the natural cooling, like
this may obtain the longer product life, the obvious low maintenance
cost, the power source initial cost does not look like the present
such expensively (present self-cooling module to be very expensive).
Thus, the choice ?remainder very big system plan also may
accept, it may safely supply power. The forced-air cooling module is counterbalanced in the
cost and the size superiority by its shortcoming (for example noise,
dust, ventilator life and reliability), but these shortcomings
certainly are not the most most important consideration questions in
fact. An outer covering designs the very bad self-cooling module
reliability compared to use the forced-air cooling the module to have
to lower a lot, because forced-air cooling module cooling has nothing
to do with with the outer covering design. Moreover, forced-air
cooling product key - semiconductor device compared to self-cooling
system 温升 lower, thus is more reliable. When the request design life surpasses for 7 years, in the
tradition does not use the ventilator. But, if allows regularly
to replace the ventilator, has the possibility to obtain designs the
life longer forced-air cooling system. If the forced-air cooling
rectification module designs has the ventilator performance monitor,
the scene is easy to replace the ventilator the characteristic, then
the permission system obtains the redundant reliability by the low
cost. Since more than 20 years both have wanted the economy to
the rectification module, and to want the long life the design request
are the conditions which the forced-air cooling product can survive. Forced-air cooling and self-cooling technology mentioned
which besides above, moreover two kind of technologies also more and
more popular: External system cooling and assistance cooling. 2.1 external systems cooling External system cooling is refers by the central
cooling system provides the air current to carry on cooling to the
rectification module. This method may obtain the power density,
moreover has avoided some shortcomings which the module power source
internal installation ventilator brings. This integrates the
supplier for the OEM application in the electrical power system which
in the entire communications system goes to bring the remarkable
profit. For instance: Central cooling system, not only provides the air current
to the electrical power system, also cools other parts of
communications system. In a system only has a central cooling
system to need to maintain, when the central cooling system breaks
down the power source still could the output energy (approximately for
full load time 60%). 2.2 auxiliary forced-air coolings The auxiliary forced-air cooling is refers to the
module cooling is provides by the interrupted movement ventilator.
When the hyperpyrexia or continues outputs the big electric
current, the ventilator can revolve. Selects this method to be
allowed to obtain the very high system integration rate, but needs
frequently to let the ventilator revolution and regularly to examine
its performance. If the ventilator work is not normal, can send
out the alarm. This method advantage includes: In does not replace in the situation, the ventilator
interrupted revolution causes the system design life to force the
forced-air cooling the module in to have to be longer than. If the consideration redundancy and the battery charge, in
the module ventilator does not transfer in the normal condition. Because the ventilator interrupted movement, the dust and
the noise question also greatly alleviates. How below explains with examples disposes the system: Rectification module: Time natural cooling capacity 30A Time auxiliary forced-air cooling capacity 50A Load: 大负?110A Battery charging current 30A Joint current 140A The request uses the N + 1 redundant backup. Must support 140A the output capacity to have to choose 3
rectification modules and 1 redundancy spare module. If 4
modules all worked (practical application) moreover the battery have
so filled the electricity, each module most 大负?the electric
current only had 110/4=27.5A, was lower than the module self-cooling
rated capacity. This time the ventilator does not transfer.
When the power cut charges to the battery, when or a module
breaks down, the system still will answer the purpose, but the
ventilator started to revolve. In the model system, the
ventilator operating time proportion is extremely low, this greatly
lengthened the product life. Moreover, according to above
example, after some module ventilator breakdown the system capacity
only reduces 10% (from 4×50A to fall to 3×50A + 30A). If uses
forces the forced-air cooling module, the system capacity will reduce
25%. Table 1 has produced under each kind of coolant conditions
typical power density. Table under 1 each kind of coolant conditions typical
power density * Coolant conditions relative capacity density Natural cooling 1.00 Forces forced-air cooling 2 to 2.5 System forced-air cooling 1.5 to 2 Auxiliary forced-air cooling 1.3 to 1.7 * The hypothesis all movements environment has the
commeasurability. 3 input voltages scope choice Is more and more important for the specific
application situation choice correct input voltage scope. In
England, in the past the usual definition input voltage scope was 216V
~ 264V (namely 240V±10%). Now tends to uses suits to the world
general voltage scope: 85V ~ 264V (or is wider). In the
practical application two 极端?(85V and 264V) all are not most
appropriate. In order to satisfy internationally on stipulates to
inputs the overtone the request, developed had the 110V power input
factor compensating circuit the rectification module, thus enable the
product to have the whole world general input voltage scope. Says regarding the mobile equipment market or the global
use equipment market, chooses the belt power factor to adjust, the
general input module is correct without doubt, but regarding fixedly
installs said, carefully chooses the input voltage scope to be able to
have the very big advantage. Will have to provide the complete
performance in the width voltage scope to be able to give the
rectification module to bring in the cost and the size remarkable
increase. This also can affect system cooling. In the
practical application the rectification module work in the 85V input
voltage time loss is time 230V two times. Obviously, sometimes must provide the complete performance
in the width voltage scope. But in certain situations, when the
input voltage is lower than some threshold value only requests in the
short time to provide the complete performance, like this does not
need to deal with the radiation issue, thus remarkably reduced the
cost and reduced the volume. If system work under 115V fixed input voltage, then moves
in 103□?V (115V - 10%) the time loss and the movement differs 15%
in the 85V time loss. The request above 85V will be able the
continuous working system when 103□?V than the continuous working
system to have to lose 15% power. The continuous working in
103□?V under certainly did not mean the system cannot reliably the
short time work under the very low voltage. The regarding this
accuracy control will be decided in the module the temperature
monitoring circuit. Chart 1 has produced between the model power loss and the
input voltage relations. 4 limits flows the characteristic The usual electrical power system has the constant
current characteristic in the entire voltage output scope, when
short-circuiting the output voltage, the electric current drop by the
broken line or the straight line. This traditional way is not
certainly ideal. Pondered the load all real characteristics may
enable the system to obtain the optimization. Adds on a correspondence electrical power system the load
is many small loads sum totals in fact. Some loads are the
resistance, some are the continuous current, some are the permanent
power, the battery also can cause the charging current change because
of the charge condition change. If the system works under the
highest battery 浮充 voltage biggest overall load electric current
(contains battery charging current) to determine its capacity, then
can the rich Yu Henduo power supply capacity. More and more many equipment use in the system in the
modern communications system to set at the DC/DC converter, it may not
provide the continuous current voltage which changes along with the
electric power supply output generatrix voltage change. This
kind of permanent power characteristic request when generatrix voltage
drop input current increase. If permanent power load in 55V time
consumes 1A, then in 40V time consumes 1□?A. But permanent
resistive load when 55V consumes 1A, when 40V only consumes 0□?A.
Carefully analyzes in the entire working voltage scope all loads
actual situation can know that, whether may be different through one
kind to the traditional continuous current limits flows the
characteristic to optimize the system. Following method may use for to determine whether uses
optimized the characteristic curve. Supposition: Time Id - 40V DC/DC biggest input current When Ir - 55V biggest resistance electric current Ib - constant battery charging current It - overall load electric current Then in 55V time: It=Id×40/55 + Ir + Ib When 40V: It=Id + Ir×40/55 + Ib Supposes the normal 浮充 voltage is 55V, the
lowest battery voltage is 40V. Example 1 Supposes: Id=100A, Ir=20A, Ib=10A When 55V: It= (100×40/55) + 20 + 10=102.7A Is equal to 5□?4kW power. When 40V: It=100 + (20×40/55) + 10=124.5A This is equal to 4□?8kW power. Example 2 Supposes: Id=50A, Ir=70A, Ib=10A When 55V: It= (50×40/55) + 70 + 10=116.4A Is equal to 6.4kW the power. When 40V: It=50 + (70×40/55) + 10=110.9A This is equal to 4.44kW the power. In example in 1, if uses the partial permanent powers
characteristic electric circuit in the module, may from 6□?5kW
(124.5×55) reduce the maximum work rate 5.64kW, saved 17% to be also
many. In the example in 2, in the entire working voltage scope,
the electric current falls very much few along with the voltage drop,
therefore suits in the rectification module has the continuous current
characteristic electric circuit. The modern switch type analysis situs technology may
easily achieve according to the overall load requests to determine the
input level, causes under the certain load combination to reduce the
always installment power also to be able to answer the purpose. |